Major orders
|
|
Andritz is to supply the electromechanical equipment for a new hydroelectric power station to Salzburg AG, Austria.
|
|
E.ON-Wasserkraft, Germany placed an order for revision and repair work at the Reisach 3 pumped storage plant.
|
|
Münchner Stadtwerke, Germany entrusted Andritz with revision and repair work at the Leitzachwerk pump storage plant.
|
|
Brigl und Bergmeister GmbH, Austria ordered a machine set with automation equipment for the water power station in the Niklasdorf mill.
|
|
|
The Business Area will supply approximately 300 process pumps for one of the world’s largest pulp mills. This is the first order the Business Area ever received from a South American customer.
|
|
A customer from Sudan placed an order for two pumping stations comprising the electromechanical equipment for 20 large-scale pump sets.
|
|
|
 |
|
|